Information maintained by the Legislative Reference Bureau Updating the database of the Illinois Compiled Statutes (ILCS) is an ongoing process. Recent laws may not yet be included in the ILCS database, but they are found on this site as Public Acts soon after they become law. For information concerning the relationship between statutes and Public Acts, refer to the Guide. Because the statute database is maintained primarily for legislative drafting purposes, statutory changes are sometimes included in the statute database before they take effect. If the source note at the end of a Section of the statutes includes a Public Act that has not yet taken effect, the version of the law that is currently in effect may have already been removed from the database and you should refer to that Public Act to see the changes made to the current law.
() 60 ILCS 1/205-141 (60 ILCS 1/205-141) Sec. 205-141. Initiating proceedings for particular locality; rates
and charges; lien; certain townships. (a) This Section applies to any township that (i) has a population between 31,500 and 32,000 according to the 2010 federal decennial census; and (ii) is located within a county that has a population between 260,000 and 265,000 according to the 2010 federal decennial census. (a-1) A township board may initiate proceedings under Sections 205-130 through
205-150 in the manner provided by Section 205-20. (b) The township board may establish a fair and reasonable rate for each
user of the waterworks system or sewerage system, or combined waterworks
and sewerage system, or improvement or extension at a rate that will be
sufficient to pay the principal and interest of any bonds issued to pay
the cost of the system, improvement, or extension and the maintenance and
operation of the system, improvement, or extension and may provide an adequate
depreciation fund for the bonds. Rates shall be established,
revised, and maintained by ordinance and become payable as the township board
determines by ordinance. (b-5) The township board may establish a fair and reasonable connection charge for each new user added to the township's waterworks system or sewerage system. (c) The charges or rates are liens upon the real estate upon or for which
sewerage service is supplied whenever the charges or rates become delinquent as
provided by the ordinance of the board fixing a delinquency date. (d) Notwithstanding any provision of law to the contrary, a cost study shall be conducted regarding the connection charge of the township: (1) before the township increases or creates a | | (2) upon the request of the supervisor or a majority
| | of the township board of the township;
|
| (3) upon the request of a majority of the mayors or
| | village presidents of the municipalities located within or substantially within the township or township's facility planning area; or
|
| (4) upon the filing with the township board of a
| | petition signed by 10% or more of the customers who have paid connection charges to the township in the previous 5 calendar years.
|
| The cost study shall be conducted by an independent entity within 6 months of action taken under paragraphs (1), (2), (3), or (4) of this subsection (d). If a cost study is requested under paragraphs (1) or (2) of this subsection, then the township shall order and pay for the cost study. If a cost study is requested under paragraphs (3) or (4) of this subsection, then the municipalities whose mayors or presidents requested the cost study under paragraph (3), or the customers who filed a petition under paragraph (4), shall choose the independent entity to conduct the cost study, order the cost study, and pay for the cost study. After performing a cost study under this subsection (d), an independent entity may not contract with any State agency, unit of local government, or non-governmental entity for goods or services within the township or township service area in the 24 months after completion of the cost study other than to perform further cost studies under this subsection (d). A township shall not be required to conduct more than one cost study in a 60 month period under paragraphs (3) or (4) of this subsection (d). The cost study must include, at a minimum, an examination of residential and commercial connection charges for the waterworks system or sewerage system, whichever applies, in at least 30 units of local government in Illinois with a similar number of customers as are connected to the township's waterworks system and sewerage system. Following the completion of the cost study, no increase or new connection charge may be imposed unless the increase or new charge is justified by the cost study. If the connection charge the township charged prior to completion of the cost study is higher than is justified by the cost study, the township shall reduce its connection charge to the amount justified by the cost study.
(e) For purposes of this Section:
"Connection charge" means any nominal charge or fee, by whatever name, assessed to recover the cost of connecting the customer's water main, sewer, or water main and sewer service line to the township's facilities, and includes only the direct and indirect costs of physically tying the service line into the township's main line in the adjoining utility easement.
"Independent entity" means an engineering firm that has not entered into a contract with any State agency, unit of local government, or non-governmental entity for goods or services within the township or township service area in the 24 months prior to being contracted to perform the cost study.
(Source: P.A. 100-528, eff. 9-22-17.)
|
60 ILCS 1/205-145
(60 ILCS 1/205-145)
Sec. 205-145. Special fund. All revenue derived from the operation of a
waterworks system or sewerage system, or combined waterworks and sewerage
system, constructed, acquired, extended, or improved to serve a particular
locality shall be set aside as collected and shall be deposited in a special
fund of the township. That fund shall be used only (i) to pay the cost of
operating and maintaining the waterworks system or sewerage system, or combined
waterworks and sewerage system, constructed, acquired, extended, or improved to
serve a particular locality, (ii) to provide an adequate depreciation fund, and
(iii) to pay the principal and interest on the bonds issued by the township
under Sections 205-130 through 205-141 for the purpose of constructing,
acquiring, extending, or improving the system.
(Source: P.A. 100-528, eff. 9-22-17.)
|
60 ILCS 1/205-150
(60 ILCS 1/205-150)
Sec. 205-150.
If, before July 18, 1972, a township (i) has constructed or
acquired a waterworks system or a sewerage system, or combined waterworks and
sewerage system, to serve a particular locality within the boundaries of the
township, (ii) has kept separate books, records, and accounts for the system or
systems, (iii) has collected rates and charges for use and service from the
users of the system or systems that are different from those collected for any
other system or systems, and (iv) has paid solely from the income and revenue
derived from the operation of the system or systems the principal of and
interest upon revenue bonds, the proceeds of which were used to pay the cost
of the construction, purchase, improvement, or extension of that system serving
a particular locality, all those acts of the township are hereby
declared to be valid, and the township may continue so to act, provided the
income and revenue of that system serving a particular locality are
sufficient to make the payments of principal and interest as they become
due. Nothing in this amendatory Act of 1972 (Public Act 77-2083) shall be
construed to impair the obligation of the ordinance authorizing the issuance of
the revenue bonds.
(Source: P.A. 77-2083; 88-62.)
|
60 ILCS 1/205-155
(60 ILCS 1/205-155)
Sec. 205-155.
Construction of Article.
This Article shall be deemed a
general law complete in itself and shall be liberally construed. Each township
upon the acquisition of a system as defined in Section 205-5 under the
provisions of this Article shall maintain and operate the system in the public
interest and for the benefit and use of the public and territory served by the
system. This Article is cumulative and in addition to any powers conferred by
any other law.
(Source: Laws 1945, p. 1745; P.A. 88-62.)
|
60 ILCS 1/Art. 207
(60 ILCS 1/Art. 207 heading)
ARTICLE 207.
TOWNSHIP
SPECIAL SERVICE AREAS
|
60 ILCS 1/207-1
(60 ILCS 1/207-1)
Sec. 207-1.
Short title.
This Article may be cited as the Township Special
Service Area Tax Law.
(Source: P.A. 90-798, eff. 12-15-98.)
|
60 ILCS 1/207-5
(60 ILCS 1/207-5)
Sec. 207-5.
Definitions.
In this Article:
"Township special service area" means a contiguous area within a township in
a
county with a population of more than 3,000,000 in which special services are
provided
in addition to those services provided generally throughout the township.
Territory is
considered contiguous even though one or more completely surrounded portions of
the
territory are excluded from the township special service area.
"Special services" means the land acquisition, development, construction, and
maintenance of streets, street lighting, sidewalks, sanitary sewer systems,
storm sewer
systems, water systems, alleys, and other necessary adjuncts within the
township special
service area.