Updating the database of the Illinois Compiled Statutes (ILCS) is an ongoing process. Recent laws may not yet be included in the ILCS database, but they are found on this site as Public Acts soon after they become law. For information concerning the relationship between statutes and Public Acts, refer to the Guide.
Because the statute database is maintained primarily for legislative drafting purposes, statutory changes are sometimes included in the statute database before they take effect. If the source note at the end of a Section of the statutes includes a Public Act that has not yet taken effect, the version of the law that is currently in effect may have already been removed from the database and you should refer to that Public Act to see the changes made to the current law.
(65 ILCS 5/11-39.2-15) Sec. 11-39.2-15. Solicitation of proposals. (a) A municipality may enter into design-build contracts. In addition to the requirements set forth in its local ordinances, when the municipality elects to use the design-build delivery method, it must issue a notice of intent to receive proposals for the project at least 14 days before issuing the request for the proposal. The municipality must publish the advance notice in the manner prescribed by ordinance, which must include posting the advance notice online on its website. The municipality may publish the notice in construction industry publications or post the notice on construction industry websites. A brief description of the proposed procurement must be included in the notice. The municipality must provide a copy of the request for proposal to any party requesting a copy. (b) The request for proposal must be prepared for each project and must contain, without limitation, the following information: (1) The name of the municipality. (2) A preliminary schedule for the completion of the | ||
| ||
(3) The proposed budget for the project, the source | ||
| ||
(4) Prequalification criteria for design-build | ||
| ||
(5) Material requirements of the contract, such as | ||
| ||
(6) The performance criteria. (7) The evaluation criteria for each phase of the | ||
| ||
(8) The number of entities that will be considered | ||
| ||
(c) The municipality may include any other relevant information that it chooses to supply. The design-build entity may rely upon the accuracy of this documentation in the development of its proposal. (d) The date that proposals are due must be at least 21 calendar days after the date of the issuance of the request for proposal. If the cost of the project is estimated to exceed $12,000,000, then the proposal due date must be at least 28 calendar days after the date of the issuance of the request for proposal. The municipality must include in the request for proposal a minimum of 30 days to develop the Phase II submissions after the selection of entities from the Phase I evaluation is completed. (Source: P.A. 103-491, eff. 1-1-24.) |