| 5 | | Civil Administrative Code of Illinois is amended by changing | 6 | | Section 2705-595 and by adding Section 2705-607 as follows: | 7 | | (20 ILCS 2705/2705-595)
| 8 | | Sec. 2705-595. Prequalification of minority-owned and | 9 | | women-owned contractors. | 10 | | (a) The Department shall, within 30 days after the | 11 | | effective date of this amendatory Act of the 96th General | 12 | | Assembly, establish a committee to review the rules for | 13 | | prequalification of contractors adopted by the Department at 44 | 14 | | Illinois Administrative Code 650. The purpose of the review is | 15 | | to determine whether the rules for prequalification operate as | 16 | | a barrier to minority-owned and women-owned contractors | 17 | | becoming prequalified to bid on or make proposals for | 18 | | Department contracts. The committee shall, in addition to | 19 | | Department staff, be constituted with membership representing | 20 | | the construction industry and minority-owned and women-owned | 21 | | contractors. The committee shall complete its work and make | 22 | | recommendations for any changes to the rules for | 23 | | prequalification to the Secretary of Transportation within 180 |
| | | SB0263 Engrossed | - 2 - | LRB100 05184 AXK 15194 b |
|
| 1 | | days after the effective date of this amendatory Act of the | 2 | | 96th General Assembly.
| 3 | | (b) The Department, in conjunction with the Capital | 4 | | Development Board, shall hold 2 public hearings to determine | 5 | | whether a more effective, efficient, and less burdensome method | 6 | | exists to prequalify an architect, engineer, or contractor. The | 7 | | hearings shall also specifically determine how the Department | 8 | | can obtain greater participation in the bidding process of | 9 | | small contractors and minority, female, disabled, and veteran | 10 | | architects, engineers, and contractors. The Department and the | 11 | | Capital Development Board shall collect data to review at the | 12 | | hearings, which shall include, but is not limited to, | 13 | | percentages and the number of minority, female, disabled, and | 14 | | veteran employees who are hired for each trade necessary for | 15 | | each project. The Department and the Capital Development Board | 16 | | shall issue their joint findings and recommendations to the | 17 | | Governor and the General Assembly no later than January 1, | 18 | | 2018. | 19 | | (Source: P.A. 96-795, eff. 7-1-10 (see Section 5 of P.A. 96-793 | 20 | | for the effective date of P.A. 96-795) .) | 21 | | (20 ILCS 2705/2705-607 new) | 22 | | Sec. 2705-607. Performance evaluation; contractor. | 23 | | (a) For purposes of this Section, "Performance Factor" | 24 | | means a numerical value determined by the contractor's | 25 | | performance evaluation in a work category during the previous |
| | | SB0263 Engrossed | - 3 - | LRB100 05184 AXK 15194 b |
|
| 1 | | year. | 2 | | (b) At the close of each construction season, the | 3 | | Department, other State agencies or authorities using | 4 | | contractors based on the prequalification standards of the | 5 | | Department, and officials of a unit of local government | 6 | | administering a contract approved for award by the Department, | 7 | | shall evaluate each contractor who performed work for them | 8 | | during the previous year as either a prime contractor or a | 9 | | subcontractor. The information shall be submitted on the | 10 | | Contractor's Annual Performance Report and shall be subject to | 11 | | disclosure under the Freedom of Information Act. The | 12 | | performance evaluation shall be based upon: | 13 | | (1) the quality of work performed for each work | 14 | | category under 44 Ill. Admin. Code 650; and | 15 | | (2) the overall execution of work measured by: | 16 | | (A) organization and prosecution of work; | 17 | | (B) cooperation with public agency personnel | 18 | | responsible for contract administration and | 19 | | inspection; | 20 | | (C) traffic control and site protection under | 21 | | contract requirements; | 22 | | (D) compliance with the Equal Employment | 23 | | Opportunity program and labor requirements; | 24 | | (E) erosion control; and | 25 | | (F) the contractor's ability to meet the Quality | 26 | | Control plan and Quality Assurance plan under contract |
| | | SB0263 Engrossed | - 4 - | LRB100 05184 AXK 15194 b |
|
| 1 | | requirements for materials production and construction | 2 | | quality control. | 3 | | (c) The performance evaluation scale is a rating from 0 to | 4 | | 8 in accordance with the following definitions: | 5 | | (1) "8" means excellent; | 6 | | (2) "7" means good; | 7 | | (3) "6" means satisfactory; | 8 | | (4) "3" means marginal; and | 9 | | (5) "0" means poor. | 10 | | (d) The quality and evaluating categories under execution | 11 | | of work are rated as follows: | 12 | | (1) to determine the contractor's quality of | 13 | | performance, the Department shall consider the project's | 14 | | durability and appearance, knowledge of supervisory | 15 | | personnel, and compliance with contract requirements and | 16 | | shall evaluate the performance based on the following | 17 | | scale: | 18 | | (A) if the contractor exceeded project | 19 | | requirements in all areas considered, he or she shall | 20 | | receive an 8; | 21 | | (B) if the contractor exceeded project | 22 | | requirements in a majority of areas considered, he or | 23 | | she shall receive a 7; | 24 | | (C) if the contractor met project requirements in | 25 | | all areas considered, he or she shall receive a 6; | 26 | | (D) if the contractor did not meet project |
| | | SB0263 Engrossed | - 5 - | LRB100 05184 AXK 15194 b |
|
| 1 | | requirements in one area considered, he or she shall | 2 | | receive a 3; and | 3 | | (E) if the contractor did not meet project | 4 | | requirements in 2 or more areas considered, he or she | 5 | | shall receive a 0; | 6 | | (2) to determine the contractor's organization and | 7 | | prosecution, the Department shall consider the | 8 | | contractor's ability to diligently prosecute work by | 9 | | planning and scheduling labor, materials, and the work of | 10 | | subcontractors on the project site and shall evaluate the | 11 | | organization and prosecution based on the following scale: | 12 | | (A) if the contractor exceeded project | 13 | | requirements in all areas considered and completed the | 14 | | project well ahead of schedule, he or she shall receive | 15 | | an 8; | 16 | | (B) if the contractor exceeded project | 17 | | requirements in a majority of areas considered and the | 18 | | project was completed slightly ahead of schedule, he or | 19 | | she shall receive a 7; | 20 | | (C) if the contractor met project requirements in | 21 | | all areas considered and the scheduled completion date | 22 | | was met, he or she shall receive a 6; | 23 | | (D) if the contractor did not meet project | 24 | | requirements in one area considered and occasionally | 25 | | did not work when conditions permitted and the | 26 | | scheduled completion date was met, he or she shall |
| | | SB0263 Engrossed | - 6 - | LRB100 05184 AXK 15194 b |
|
| 1 | | receive a 3; and | 2 | | (E) if the contractor did not meet project | 3 | | requirements in 2 or more areas considered and the | 4 | | scheduled completion date was not met, he or she shall | 5 | | receive a 0; | 6 | | (3) to determine the contractor's cooperation, the | 7 | | Department shall consider the contractor's willingness to | 8 | | negotiate contract disputes, to respond to reasonable | 9 | | requests by the resident engineer, and to respond to | 10 | | various correspondence from the Department and shall | 11 | | evaluate the cooperation based on the following scale: | 12 | | (A) if the contractor exceeded project | 13 | | requirements in all areas considered, he or she shall | 14 | | receive an 8; | 15 | | (B) if the contractor exceeded project | 16 | | requirements in a majority of areas considered, he or | 17 | | she shall receive a 7; | 18 | | (C) if the contractor met project requirements in | 19 | | all areas considered, he or she shall receive a 6; | 20 | | (D) if the contractor did not meet project | 21 | | requirements in one area considered, he or she shall | 22 | | receive a 3; and | 23 | | (E) if the contractor did not meet project | 24 | | requirements in 2 or more areas considered, he or she | 25 | | shall receive a 0; | 26 | | (4) to determine the project's traffic control and site |
| | | SB0263 Engrossed | - 7 - | LRB100 05184 AXK 15194 b |
|
| 1 | | protection, the Department shall consider the appearance | 2 | | of traffic control devices, the response to repair | 3 | | deficient devices, and the contractor's willingness to | 4 | | comply with the Traffic Control Plan and shall evaluate | 5 | | based on the following scale: | 6 | | (A) if the contractor exceeded project | 7 | | requirements in all areas considered, he or she shall | 8 | | receive an 8; | 9 | | (B) if the contractor exceeded project | 10 | | requirements in a majority of areas considered, he or | 11 | | she shall receive a 7; | 12 | | (C) if the contractor met project requirements in | 13 | | all areas considered, he or she shall receive a 6; | 14 | | (D) if the contractor did not meet project | 15 | | requirements in one area considered, he or she shall | 16 | | receive a 3; and | 17 | | (E) if the contractor did not meet project | 18 | | requirements in 2 or more areas considered or the | 19 | | contractor committed an act or omission which | 20 | | seriously compromised the safety of the public, he or | 21 | | she shall receive a 0; | 22 | | (5) to determine the contractor's compliance with the | 23 | | Equal Employment Opportunity program and labor | 24 | | requirements, the Department shall evaluate the compliance | 25 | | based on the following scale: | 26 | | (A) if the contractor exceeded project |
| | | SB0263 Engrossed | - 8 - | LRB100 05184 AXK 15194 b |
|
| 1 | | requirements, he or she shall receive an 8; | 2 | | (B) if the contractor met project requirements | 3 | | through extraordinary effort and initiative, he or she | 4 | | shall receive a 7; | 5 | | (C) if the contractor met project requirements | 6 | | with minimum effort and initiative, he or she shall | 7 | | receive a 6; | 8 | | (D) if the contractor met project requirements, | 9 | | but had to be motivated by Department personnel, he or | 10 | | she shall receive a 3; and | 11 | | (E) if the contractor did not meet project | 12 | | requirements, he or she shall receive a 0; | 13 | | (6) to determine the project's erosion control, the | 14 | | Department shall consider the contractor's compliance with | 15 | | the project's erosion control plan and all pertinent | 16 | | federal and State laws, permits, rules, and regulations and | 17 | | shall evaluate based on the following scale: | 18 | | (A) if the contractor exceeded project | 19 | | requirements, he or she shall receive an 8; | 20 | | (B) if the contractor exceeded project | 21 | | requirements in a majority of the areas, he or she | 22 | | shall receive a 7; | 23 | | (C) if the contractor met project requirements in | 24 | | all areas, he or she shall receive a 6; | 25 | | (D) if the contractor did not meet the project | 26 | | requirements in one area considered, he or she shall |
| | | SB0263 Engrossed | - 9 - | LRB100 05184 AXK 15194 b |
|
| 1 | | receive a 3; and | 2 | | (E) if the contractor did not meet the contract | 3 | | requirements in 2 or more areas, he or she shall | 4 | | receive a 0; | 5 | | (7) to determine the contractor's ability to meet the | 6 | | Quality Control plan and Quality Assurance plan, the | 7 | | Department shall consider the contractor's ability to meet | 8 | | a Quality Control plan and Quality Assurance plan | 9 | | inspection, testing, and documentation requirements, to | 10 | | take control of the product, to take corrective action, and | 11 | | to communicate production and construction issued to | 12 | | Department personnel and shall evaluate based on the | 13 | | following scale: | 14 | | (A) if the contractor exceeded Quality Control | 15 | | plan and Quality Assurance plan requirements in all | 16 | | areas considered, he or she shall receive an 8; | 17 | | (B) if the contractor exceeded Quality Control | 18 | | plan and Quality Assurance plan requirements in a | 19 | | majority of areas considered, he or she shall receive a | 20 | | 7; | 21 | | (C) if the contractor met Quality Control plan and | 22 | | Quality Assurance plan requirements in all areas | 23 | | considered, he or she shall receive a 6; | 24 | | (D) if the contractor did not meet Quality Control | 25 | | plan and Quality Assurance plan requirements in one | 26 | | area considered, he or she shall receive a 3; and |
| | | SB0263 Engrossed | - 10 - | LRB100 05184 AXK 15194 b |
|
| 1 | | (E) if the contractor did not meet Quality Control | 2 | | plan and Quality Assurance plan requirements in 2 or | 3 | | more areas considered, he or she shall receive a 0. | 4 | | (e) The Department shall calculate the Performance Factor | 5 | | by first determining the Project Cost Ratio for the relevant | 6 | | work category. The Project Cost Ratio is the ratio of the value | 7 | | of all contracts being evaluated to the value of all contracts | 8 | | performed. The Department shall establish a weighted | 9 | | performance evaluation value for each performance evaluation | 10 | | completed by determining the product of the Project Cost Ratio, | 11 | | the rating for quality given on the relevant performance | 12 | | evaluation, and the averaged ratings for the execution given on | 13 | | the relevant performance evaluation divided by 6. Finally, the | 14 | | Department shall divide the summation of all weighted | 15 | | performance evaluation values by 6 to arrive at the Performance | 16 | | Factor. | 17 | | (f) A work rating shall be subject to denial or revocation | 18 | | if the summation of all weighted performance evaluation values | 19 | | for a work rating category is less than 6 for 2 successive | 20 | | years. A work rating shall be subject to denial or revocation | 21 | | if the summation of all weighted performance evaluation values | 22 | | for a work rating category is less than 3 for one year. | 23 | | (g) The Department shall evaluate performance on any | 24 | | individual contract or group of contracts for purposes of | 25 | | determining the current responsibility of a contractor when the | 26 | | Engineer of Construction has determined that performance on any |
| | | SB0263 Engrossed | - 11 - | LRB100 05184 AXK 15194 b |
|
| 1 | | contract or contracts may not be acceptable and that an | 2 | | immediate evaluation is necessary to assess the responsibility | 3 | | of a contractor in order to protect the interests of the State | 4 | | in sound procurement practices. If the evaluation ordered by | 5 | | the Engineer of Construction results in the quality of work or | 6 | | the average overall execution of work ratings being rated at | 7 | | less than 3, the work ratings shall be revoked. | 8 | | (h) If a contractor receives a Quality of Work Rating of 0 | 9 | | for any work category being evaluated on any one contract, the | 10 | | work rating shall be revoked. | 11 | | (i) The Department shall notify the contractor of the | 12 | | performance evaluation in writing within 14 days of completion | 13 | | of the evaluation with a detailed explanation of any | 14 | | substandard items. If a performance evaluation results in a | 15 | | denied, reduced, or revoked work rating, the contractor may | 16 | | proceed with the review procedures under 44 Ill. Admin. Code | 17 | | 650.150. | 18 | | (j) If an applicant did not have a contract with the | 19 | | Department in the previous year, the last evaluation issued | 20 | | within a 5-year period shall be used. If an applicant has not | 21 | | had an evaluation in the last 5 years or is applying for an | 22 | | initial rating in a category and lists no public agencies or | 23 | | private customers as references, a Performance Factor of "1" | 24 | | shall be used until an actual evaluation is made. | 25 | | (k) As a component of the Auditor's General biennial | 26 | | compliance examination of the Department, the Auditor General |
| | | SB0263 Engrossed | - 12 - | LRB100 05184 AXK 15194 b |
|
| 1 | | shall review the Department's compliance with the requirements | 2 | | under this Section. Upon completion of the examination and | 3 | | release of the results to the Department, the Auditor General | 4 | | shall publish the results on its website. | 5 | | Section 10. The Criminal Code of 2012 is amended by adding | 6 | | Section 33E-15.5 as follows: | 7 | | (720 ILCS 5/33E-15.5 new) | 8 | | Sec. 33E-15.5. Manipulation of work ratings. | 9 | | (a) Any person who knowingly manipulates a work rating | 10 | | factor for a contractor or subcontractor under Section 2705-907 | 11 | | of the Department of Transportation Law of the Civil | 12 | | Administrative Code of Illinois that results in a rating | 13 | | disqualifying or qualifying a contractor or subcontractor who | 14 | | would have been otherwise qualified or disqualified commits | 15 | | manipulation of work ratings. A charge of manipulation of work | 16 | | ratings under this Section shall be investigated by the | 17 | | Department of Transportation Division of Internal | 18 | | Investigation. | 19 | | (b) Sentence. Manipulation of work ratings is a Class 4 | 20 | | felony.
| 21 | | Section 99. Effective date. This Act takes effect upon | 22 | | becoming law.
|
|