Illinois General Assembly - Full Text of HB2664
Illinois General Assembly

Previous General Assemblies

Full Text of HB2664  100th General Assembly

HB2664ham001 100TH GENERAL ASSEMBLY

Rep. William Davis

Filed: 4/21/2017

 

 


 

 


 
10000HB2664ham001LRB100 08773 MLM 25371 a

1
AMENDMENT TO HOUSE BILL 2664

2    AMENDMENT NO. ______. Amend House Bill 2664 by replacing
3everything after the enacting clause with the following:
 
4    "Section 5. The State Prompt Payment Act is amended by
5changing Section 7 as follows:
 
6    (30 ILCS 540/7)   (from Ch. 127, par. 132.407)
7    Sec. 7. Payments to subcontractors and material suppliers.
8    (a) When a State official or agency responsible for
9administering a contract submits a voucher to the Comptroller
10for payment to a contractor, that State official or agency
11shall promptly make available electronically the voucher
12number, the date of the voucher, and the amount of the voucher.
13The State official or agency responsible for administering the
14contract shall provide subcontractors and material suppliers,
15known to the State official or agency, with instructions on how
16to access the electronic information.

 

 

10000HB2664ham001- 2 -LRB100 08773 MLM 25371 a

1    (a-5) When a contractor receives any payment, the
2contractor shall pay each subcontractor and material supplier
3in proportion to the work completed by each subcontractor and
4material supplier its their application or pay estimate, plus
5interest received under this Act, less any retention. When a
6contractor receives any payment, the contractor shall pay each
7lower-tiered subcontractor and material supplier and each
8subcontractor and material supplier shall make payment to its
9own respective subcontractors and material suppliers. If the
10contractor receives less than the full payment due under the
11public construction contract, the contractor shall be
12obligated to disburse on a pro rata basis those funds received,
13plus interest received under this Act, with the contractor,
14subcontractors and material suppliers each receiving a
15prorated portion based on the amount of payment each has
16earned. When, however, the State official or agency public
17owner does not release the full payment due under the contract
18because there are specific areas of work or materials the State
19agency or official has determined contractor is rejecting or
20because the contractor has otherwise determined such areas are
21not suitable for payment, then those specific subcontractors or
22material suppliers involved shall not be paid for that portion
23of work rejected or deemed not suitable for payment and all
24other subcontractors and suppliers shall be paid based upon the
25amount of payment each has earned in full, plus interest
26received under this Act.

 

 

10000HB2664ham001- 3 -LRB100 08773 MLM 25371 a

1    (a-10) For construction contracts with the Department of
2Transportation, the contractor, subcontractor, or material
3supplier, regardless of tier, shall not offset, decrease, or
4diminish payment or payments that are due to its subcontractors
5or material suppliers without reasonable cause.
6    A contractor, who refuses to make prompt payment, in whole
7or in part, shall provide to the subcontractor or material
8supplier and the public owner or its agent, a written notice of
9that refusal. The written notice shall be made by a contractor
10no later than 5 calendar days after payment is received by the
11contractor. The written notice shall identify the Department of
12Transportation's contract, any subcontract or material
13purchase agreement, a detailed reason for refusal, the value of
14the payment to be withheld, and the specific remedial actions
15required of the subcontractor or material supplier so that
16payment may be made. Written notice of refusal may be given in
17a form and method which is acceptable to the parties and public
18owner.
19    (b) If the contractor, without reasonable cause, fails to
20make full payment of amounts due under subsection (a) to its
21his subcontractors and material suppliers within 15 calendar
22days after receipt of payment from the State official or agency
23under the public construction contract, the contractor shall
24pay to its his subcontractors and material suppliers, in
25addition to the payment due them, interest in the amount of 2%
26per month, calculated from the expiration of the 15-day period

 

 

10000HB2664ham001- 4 -LRB100 08773 MLM 25371 a

1until fully paid. This subsection shall further also apply to
2any payments made by subcontractors and material suppliers to
3their subcontractors and material suppliers and to all payments
4made to lower tier subcontractors and material suppliers
5throughout the contracting chain.
6        (1) If a contractor, without reasonable cause, fails to
7    make payment in full as provided in subsection (a-5) (a)
8    within 15 calendar days after receipt of payment under the
9    public construction contract, any subcontractor or
10    material supplier to whom payments are owed may file a
11    written notice and request for administrative hearing with
12    the State official or agency setting forth the amount owed
13    by the contractor and the contractor's failure to timely
14    pay the amount owed. The written notice and request for
15    administrative hearing shall identify the public
16    construction contract, the contractor, and the amount
17    owed, and shall contain a sworn statement or attestation to
18    verify the accuracy of the notice. The notice and request
19    for administrative hearing shall be filed with the State
20    official for the public construction contract, with a copy
21    of the notice concurrently provided to the contractor.
22    Notice to the State official may be made by certified or
23    registered mail, messenger service, or personal service,
24    and must include proof of delivery to the State official.
25        (2) The State official or agency, within 15 calendar
26    days after receipt of a subcontractor's or material

 

 

10000HB2664ham001- 5 -LRB100 08773 MLM 25371 a

1    supplier's written notice and request for administrative
2    hearing of the failure to receive payment from the
3    contractor, shall hold a hearing convened by an
4    administrative law judge to determine whether the
5    contractor withheld payment, without reasonable cause,
6    from the subcontractors or and material suppliers and what
7    amount, if any, is due to the subcontractors or and
8    material suppliers, and the reasonable cause or causes
9    asserted by the contractor. The State official or agency
10    shall provide appropriate notice to the parties of the
11    date, time, and location of the hearing. Each contractor,
12    subcontractor, or and material supplier has the right to be
13    represented by counsel at a the hearing and to
14    cross-examine witnesses and challenge documents. Upon the
15    request of the subcontractor or material supplier and a
16    showing of good cause, reasonable continuances may be
17    granted by the administrative law judge.
18        (3) Upon If there is a finding by the administrative
19    law judge that the contractor failed to make payment in
20    full, without reasonable cause, as provided in subsection
21    (a-10) (a), then the administrative law judge shall, in
22    writing, order direct the contractor to pay the amount owed
23    to the subcontractors or and material suppliers plus
24    interest within 15 calendar days after the order finding.
25        (4) If a contractor fails to make full payment as
26    ordered under paragraph (3) of this subsection (b) within

 

 

10000HB2664ham001- 6 -LRB100 08773 MLM 25371 a

1    15 days after the administrative law judge's order finding,
2    then the contractor shall be barred from entering into a
3    State public construction contract for a period of one year
4    beginning on the date of the administrative law judge's
5    order finding.
6        (5) If, on 2 or more occasions within a 3-calendar-year
7    period, there is a finding by an administrative law judge
8    that the contractor failed to make payment in full, without
9    reasonable cause, and a written order was issued to a
10    contractor under paragraph (3) of this subsection (b), then
11    the contractor shall be barred from entering into a State
12    public construction contract for a period of 6 months
13    beginning on the date of the administrative law judge's
14    second written order, even if the payments required under
15    the orders were made in full.
16        (6) If a contractor fails to make full payment as
17    ordered under paragraph (4) of this subsection (b), the
18    subcontractor or material supplier may, within 30 days of
19    the date of that order, petition the State agency for an
20    order for reasonable attorney's fees and costs incurred in
21    the prosecution of the action under this subsection (b).
22    Upon that petition and taking of additional evidence, as
23    may be required, the administrative law judge may issue a
24    supplemental order directing the contractor to pay those
25    reasonable attorney's fees and costs.
26        (7) The written order of the administrative law judge

 

 

10000HB2664ham001- 7 -LRB100 08773 MLM 25371 a

1    shall be final and appealable under the Administrative
2    Review Law.
3    (c) This Section shall not be construed to in any manner
4diminish, negate, or interfere with the
5contractor-subcontractor or contractor-material supplier
6relationship or commercially useful function.
7    (d) This Section shall not preclude, bar, or stay the
8rights, remedies, and defenses available to the parties by way
9of the operation of their contract, purchase agreement, the
10Mechanics Lien Act, or the Public Construction Bond Act.
11    (e) State officials and agencies may adopt rules as may be
12deemed necessary in order to establish the formal procedures
13required under this Section.
14    (f) As used in this Section,
15    "Payment" means the discharge of an obligation in money or
16other valuable consideration or thing delivered in full or
17partial satisfaction of an obligation to pay. "Payment" shall
18include interest paid pursuant to this Act.
19    "Reasonable cause" may include, but is not limited to,
20unsatisfactory workmanship or materials; failure to provide
21documentation required by the contract, subcontract, or
22material purchase agreement; claims made against the
23Department of Transportation or the subcontractor pursuant to
24subsection (c) of Section 23 of the Mechanics Lien Act or the
25Public Construction Bond Act; judgments, levies, garnishments,
26or other court-ordered assessments or offsets in favor of the

 

 

10000HB2664ham001- 8 -LRB100 08773 MLM 25371 a

1Department of Transportation or other State agency entered
2against a subcontractor or material supplier. "Reasonable
3cause" does not include payments issued to the contractor that
4create a negative or reduced valuation pay application or pay
5estimate due to a reduction of contract quantities or work not
6performed or provided by the subcontractor or material
7supplier; the interception or withholding of funds for reasons
8not related to the subcontractor's or material supplier's work
9on the contract; anticipated claims or assessments of third
10parties not a party related to the contract or subcontract;
11asserted claims or assessments of third parties that are not
12authorized by court order, administrative tribunal, or
13statute. "Reasonable cause" further does not include the
14withholding, offset, or reduction of payment, in whole or in
15part, due to the assessment of liquidated damages or penalties
16assessed by the Department of Transportation against the
17contractor, unless the subcontractor's performance or supplied
18materials were the sole and proximate cause of the liquidated
19damage or penalty.
20(Source: P.A. 94-672, eff. 1-1-06; 94-972, eff. 7-1-07.)".