SB2485 96TH GENERAL ASSEMBLY

  
  

 


 
96TH GENERAL ASSEMBLY
State of Illinois
2009 and 2010
SB2485

 

Introduced 10/15/2009, by Sen. William R. Haine

 

SYNOPSIS AS INTRODUCED:
 
220 ILCS 5/8-406   from Ch. 111 2/3, par. 8-406
220 ILCS 5/8-406.1 new
220 ILCS 5/8-509   from Ch. 111 2/3, par. 8-509
220 ILCS 5/8-510   from Ch. 111 2/3, par. 8-510

    Amends the Public Utilities Act. Provides that specified provisions concerning a certificate of public convenience and necessity do not apply to an electric utility providing transmission service connections located within its certified or service territory in the usual course of business or transmission system extensions approved pursuant to a specific provision. Adds a provision concerning an alternative procedure for obtaining a certificate of public convenience and necessity for specified transmission line extensions not in the usual course of business. Includes land use studies as an activity requiring a certificate of public convenience and necessity. Effective immediately.


LRB096 14944 MJR 29837 b

FISCAL NOTE ACT MAY APPLY

 

 

A BILL FOR

 

SB2485 LRB096 14944 MJR 29837 b

1     AN ACT concerning utilities.
 
2     Be it enacted by the People of the State of Illinois,
3 represented in the General Assembly:
 
4     Section 5. The Public Utilities Act is amended by changing
5 Sections 8-406, 8-509, and 8-510 and by adding Section 8-406.1
6 as follows:
 
7     (220 ILCS 5/8-406)  (from Ch. 111 2/3, par. 8-406)
8     Sec. 8-406. Certificate of public convenience and
9 necessity.
10     (a) No public utility not owning any city or village
11 franchise nor engaged in performing any public service or in
12 furnishing any product or commodity within this State as of
13 July 1, 1921 and not possessing a certificate of public
14 convenience and necessity from the Illinois Commerce
15 Commission, the State Public Utilities Commission or the Public
16 Utilities Commission, at the time this amendatory Act of 1985
17 goes into effect, shall transact any business in this State
18 until it shall have obtained a certificate from the Commission
19 that public convenience and necessity require the transaction
20 of such business.
21     (b) No public utility shall begin the construction of any
22 new plant, equipment, property or facility which is not in
23 substitution of any existing plant, equipment, property or

 

 

SB2485 - 2 - LRB096 14944 MJR 29837 b

1 facility or any extension or alteration thereof or in addition
2 thereto, unless and until it shall have obtained from the
3 Commission a certificate that public convenience and necessity
4 require such construction. Whenever after a hearing the
5 Commission determines that any new construction or the
6 transaction of any business by a public utility will promote
7 the public convenience and is necessary thereto, it shall have
8 the power to issue certificates of public convenience and
9 necessity. The Commission shall determine that proposed
10 construction will promote the public convenience and necessity
11 only if the utility demonstrates: (1) that the proposed
12 construction is necessary to provide adequate, reliable, and
13 efficient service to its customers and is the least-cost means
14 of satisfying the service needs of its customers or that the
15 proposed construction will promote the development of an
16 effectively competitive electricity market that operates
17 efficiently, is equitable to all customers, and is the least
18 cost means of satisfying those objectives; (2) that the utility
19 is capable of efficiently managing and supervising the
20 construction process and has taken sufficient action to ensure
21 adequate and efficient construction and supervision thereof;
22 and (3) that the utility is capable of financing the proposed
23 construction without significant adverse financial
24 consequences for the utility or its customers.
25     This Section does not apply to an electric utility
26 providing transmission service connections located within its

 

 

SB2485 - 3 - LRB096 14944 MJR 29837 b

1 certified or service territory in the usual course of business
2 or transmission system extensions approved under Section
3 8-406.1. Transmission service connections made in the usual
4 course of business include any of the following:
5         (i) the replacement or upgrading of existing electric
6     transmission line, notwithstanding its voltage level,
7     capacity, or length;
8         (ii) the relocation of existing electric transmission
9     line, notwithstanding its voltage level, capacity, or
10     length, to accommodate construction or expansion of a
11     roadway or other transportation infrastructure;
12         (iii) an electric transmission line that is
13     constructed solely to serve a single customer's premises
14     and that will pass under or over the premises owned by the
15     customer to be served or under or over premises for which
16     the customer has secured the necessary right of way; or
17         (iv) the construction of an electric transmission line
18     having a capacity of 100 kilovolts or more and a length of
19     not more than 5,280 feet.
20     (c) After the effective date of this amendatory Act of
21 1987, no construction shall commence on any new nuclear power
22 plant to be located within this State, and no certificate of
23 public convenience and necessity or other authorization shall
24 be issued therefor by the Commission, until the Director of the
25 Illinois Environmental Protection Agency finds that the United
26 States Government, through its authorized agency, has

 

 

SB2485 - 4 - LRB096 14944 MJR 29837 b

1 identified and approved a demonstrable technology or means for
2 the disposal of high level nuclear waste, or until such
3 construction has been specifically approved by a statute
4 enacted by the General Assembly.
5     As used in this Section, "high level nuclear waste" means
6 those aqueous wastes resulting from the operation of the first
7 cycle of the solvent extraction system or equivalent and the
8 concentrated wastes of the subsequent extraction cycles or
9 equivalent in a facility for reprocessing irradiated reactor
10 fuel and shall include spent fuel assemblies prior to fuel
11 reprocessing.
12     (d) In making its determination, the Commission shall
13 attach primary weight to the overall cost, cost of materials,
14 or cost savings to the customers of the utility. The Commission
15 may consider any or all factors which will or may affect such
16 overall cost, cost of materials, or cost savings.
17     (e) The Commission may issue a temporary certificate which
18 shall remain in force not to exceed one year in cases of
19 emergency, to assure maintenance of adequate service or to
20 serve particular customers, without notice or hearing, pending
21 the determination of an application for a certificate, and may
22 by regulation exempt from the requirements of this Section
23 temporary acts or operations for which the issuance of a
24 certificate will not be required in the public interest.
25     A public utility shall not be required to obtain but may
26 apply for and obtain a certificate of public convenience and

 

 

SB2485 - 5 - LRB096 14944 MJR 29837 b

1 necessity pursuant to this Section with respect to any matter
2 as to which it has received the authorization or order of the
3 Commission under the Electric Supplier Act, and any such
4 authorization or order granted a public utility by the
5 Commission under that Act shall as between public utilities be
6 deemed to be, and shall have except as provided in that Act the
7 same force and effect as, a certificate of public convenience
8 and necessity issued pursuant to this Section.
9     No electric cooperative shall be made or shall become a
10 party to or shall be entitled to be heard or to otherwise
11 appear or participate in any proceeding initiated under this
12 Section for authorization of power plant construction and as to
13 matters as to which a remedy is available under The Electric
14 Supplier Act.
15     (f) Such certificates may be altered or modified by the
16 Commission, upon its own motion or upon application by the
17 person or corporation affected. Unless exercised within a
18 period of 2 years from the grant thereof authority conferred by
19 a certificate of convenience and necessity issued by the
20 Commission shall be null and void.
21     No certificate of public convenience and necessity shall be
22 construed as granting a monopoly or an exclusive privilege,
23 immunity or franchise.
24 (Source: P.A. 95-700, eff. 11-9-07.)
 
25     (220 ILCS 5/8-406.1 new)

 

 

SB2485 - 6 - LRB096 14944 MJR 29837 b

1     Sec. 8-406.1. Certificate of public convenience and
2 necessity; alternative procedure for specified transmission
3 line extensions not in the usual course of business.
4     (a) An electric utility may seek an alternative certificate
5 of public convenience and necessity for the construction of any
6 new electric transmission lines having a capacity of 100
7 kilovolts or more and a continuous length of more than 5,280
8 feet.
9     (b) An application for a certificate of public convenience
10 and necessity under this Section shall include all information
11 related to the manner and time of construction and other
12 information in support of the alternative treatment afforded by
13 this Section. The application shall also provide information
14 required under paragraphs (c), (e), (g), and (j) of 18 CFR
15 50.7, as now in effect and as amended from time to time, and
16 the application shall include an application fee of $100,000 to
17 be paid into the Public Utility Fund at the time the Chief
18 Clerk of the Commission deems the application complete and
19 accepts the filing. The electric utility shall publish notice
20 of its application in the official State newspaper within 10
21 days after the date of the application's filing.
22     (c) The Commission shall grant the application for a
23 certificate of public convenience and necessity pursuant to
24 this Section if, based upon the application filed with the
25 Commission, it finds all of the following:
26         (i) That the transmission line is the least cost means

 

 

SB2485 - 7 - LRB096 14944 MJR 29837 b

1     of satisfying the service needs of the electric utility's
2     customers or that the electric utility's proposed
3     construction of the line will promote the development of an
4     effectively competitive electricity market that operates
5     efficiently and is equitable to all customers.
6         (ii) That the electric utility is capable of
7     efficiently managing and supervising the construction
8     process and has taken sufficient action to ensure adequate
9     and efficient construction and supervision.
10         (iii) That the electric utility is capable of financing
11     the proposed construction without significant adverse
12     financial consequences for the utility or its customers.
13     (d) The Commission shall issue its decision with findings
14 of fact and conclusions of law granting or denying the
15 application no later than 120 days after the application is
16 filed.
17     (e) The electric utility shall pay a one-time construction
18 fee to each county in which the transmission line is
19 constructed pursuant to a certificate granted under this
20 Section. The construction fee shall be $20,000 per mile of
21 transmission line constructed in that county, or proportionate
22 fraction thereof, and it shall be paid to the county treasurer
23 30 days after completion of the construction of the
24 transmission line constructed in that county pursuant to the
25 certificate of public convenience and necessity granted under
26 this Section. Counties receiving a payment under this Section

 

 

SB2485 - 8 - LRB096 14944 MJR 29837 b

1 from an electric utility may distribute all or portions of the
2 fee to local taxing districts in that county who are contiguous
3 to the transmission line.
4     (f) A decision denying the application under this Section
5 shall not act as a bar to the electric utility's seeking a
6 certificate pursuant to the provisions of Section 8-406 of this
7 Act.
8     (g) Notwithstanding any other provisions of this Act, a
9 decision granting a certificate under this Section shall
10 include an order pursuant to Section 8-503 of this Act
11 authorizing or directing the construction of the electric
12 transmission line as approved by the Commission, in the manner
13 and within the time specified in the order.
 
14     (220 ILCS 5/8-509)  (from Ch. 111 2/3, par. 8-509)
15     Sec. 8-509. When necessary for the construction of any
16 alterations, additions, extensions or improvements ordered or
17 authorized under Section 8-406.1, 8-503, or 12-218 of this Act,
18 any public utility may enter upon, take or damage private
19 property in the manner provided for by the law of eminent
20 domain.
21     This Section applies to the exercise of eminent domain
22 powers by telephone companies or telecommunications carriers
23 only when the facilities to be constructed are intended to be
24 used in whole or in part for providing one or more intrastate
25 telecommunications services classified as "noncompetitive"

 

 

SB2485 - 9 - LRB096 14944 MJR 29837 b

1 under Section 13-502 in a tariff filed by the condemnor. The
2 exercise of eminent domain powers by telephone companies or
3 telecommunications carriers in all other cases shall be
4 governed solely by "An Act relating to the powers, duties and
5 property of telephone companies", approved May 16, 1903, as now
6 or hereafter amended.
7 (Source: P.A. 86-221.)
 
8     (220 ILCS 5/8-510)  (from Ch. 111 2/3, par. 8-510)
9     Sec. 8-510. Land surveys and land use studies. For the
10 purpose of making land surveys and land use studies, any public
11 utility that has been granted a certificate of public
12 convenience and necessity by, or received an order under
13 Section 8-503 or 8-406.1 of this Act from, the Commission may,
14 30 days after providing written notice to the owner thereof by
15 registered mail, enter upon the property of any owner who has
16 refused permission for entrance upon that property, but subject
17 to responsibility for all damages which may be inflicted
18 thereby.
19 (Source: P.A. 90-561, eff. 12-16-97.)
 
20     Section 99. Effective date. This Act takes effect upon
21 becoming law.