Full Text of HB1013 96th General Assembly
HB1013enr 96TH GENERAL ASSEMBLY
|
|
|
HB1013 Enrolled |
|
LRB096 03878 JAM 13912 b |
|
| 1 |
| AN ACT concerning State buildings.
| 2 |
| Be it enacted by the People of the State of Illinois,
| 3 |
| represented in the General Assembly:
| 4 |
| Section 1. Short title. This Act may be cited as the Green | 5 |
| Buildings Act. | 6 |
| Section 5. Findings.
The General Assembly finds that an | 7 |
| efficient green building plan is essential to: | 8 |
| (1) reduce the increasing costs of energy for public | 9 |
| buildings and reduce the State's overall energy usage; | 10 |
| (2) preserve the environment and make State buildings | 11 |
| better for those who work and study in them, as well as the | 12 |
| area around them; and | 13 |
| (3) cut pollution, moderate peak energy demand, better | 14 |
| assure the reliability of energy studies, and stabilize energy | 15 |
| costs.
| 16 |
| Section 10. Definitions. In this Act: | 17 |
| "Board" means the Capital Development Board. | 18 |
| "USGBC" means the United States Green Building Council. | 19 |
| "LEED" means the USGBC Leadership in Energy and | 20 |
| Environmental Design green building rating standard. | 21 |
| "GBI" means The Green Building Initiative. | 22 |
| "Green Globes" means the GBI green building construction |
|
|
|
HB1013 Enrolled |
- 2 - |
LRB096 03878 JAM 13912 b |
|
| 1 |
| model. | 2 |
| "Major renovation" means a project with a construction | 3 |
| budget that equals 40% or more of the building's current | 4 |
| replacement cost.
| 5 |
| Section 15. Green Buildings Standards.
| 6 |
| (a) All new State-funded building construction and major | 7 |
| renovations of existing State-owned facilities are required to | 8 |
| seek LEED, Green Globes, or equivalent certification. | 9 |
| (b) All construction and major renovation projects, | 10 |
| regardless of size, must achieve the highest level of | 11 |
| certification practical within the project budget. | 12 |
| (1) New buildings and major renovations of less than | 13 |
| 10,000 square feet must meet the highest standard of the | 14 |
| Leadership in Energy and Environmental Design's rating | 15 |
| system for new commercial construction and major | 16 |
| renovation projects, as established by the United States | 17 |
| Green Building Council, or an equivalent standard, | 18 |
| including, but not limited to, the Green Building | 19 |
| Initiative's Green Globes USA design program. USGBC LEED, | 20 |
| GBI Green Globes, or the equivalent certification is not | 21 |
| required. | 22 |
| (2) New buildings and major renovations of 10,000 | 23 |
| square feet or more must achieve the silver building rating | 24 |
| of the Leadership in Energy and Environmental Design's | 25 |
| rating system for new commercial construction and major |
|
|
|
HB1013 Enrolled |
- 3 - |
LRB096 03878 JAM 13912 b |
|
| 1 |
| renovation projects, as established by the United States | 2 |
| Green Building Council, or an equivalent standard, | 3 |
| including, but not limited to, a two-globe rating in the | 4 |
| Green Globes USA design program. USGBC LEED, GBI Green | 5 |
| Globes, or the equivalent certification is required. | 6 |
| (c) Exemptions to these standards are buildings that are | 7 |
| not "comfort" conditioned as determined by the Board. However, | 8 |
| the project design team must document and incorporate all | 9 |
| appropriate sustainable building methods, strategies, and | 10 |
| technologies in the final design. | 11 |
| (d) State agencies and the project design team may apply to | 12 |
| the Board for a waiver from these standards. | 13 |
| (e) Waivers shall be granted by the Board or an appropriate | 14 |
| agency when the applicant can demonstrate and document:
| 15 |
| (1) An unreasonable financial burden, taking into | 16 |
| account the operating and construction costs over the life | 17 |
| of the building and the total cost of ownership of the | 18 |
| building. | 19 |
| (2) An unreasonable impediment to construction. | 20 |
| (3) The standards would impair the principal function | 21 |
| of the building. | 22 |
| (4) The standards would compromise the historic nature | 23 |
| of the structure. | 24 |
| Documentation on the submittal must include at a minimum: | 25 |
| (1) Life cycle cost analysis. | 26 |
| (2) Energy modeling. |
|
|
|
HB1013 Enrolled |
- 4 - |
LRB096 03878 JAM 13912 b |
|
| 1 |
| The design team must provide the documentation for the new | 2 |
| project to confirm that LEED, Green Globes, or the equivalent | 3 |
| construction standards have been followed. | 4 |
| (f) In addition to any required LEED, Green Globes, or the | 5 |
| equivalent criteria, the Board shall require that all projects | 6 |
| referenced in subsection (a) implement at least one LEED | 7 |
| alternative transportation criterion for public transportation | 8 |
| or bicycle access. | 9 |
| (g) The green building standards contained in this Act | 10 |
| shall be analyzed and evaluated by the Board 5 years after the | 11 |
| effective date of this Act or upon the completion of 10 Board | 12 |
| green projects, whichever comes first. | 13 |
| Section 99. Effective date. This Act takes effect upon | 14 |
| becoming law.
|
|