Public Act 0141 101ST GENERAL ASSEMBLY |
Public Act 101-0141 |
| HB2491 Enrolled | LRB101 09658 CPF 54757 b |
|
|
AN ACT concerning safety.
|
Be it enacted by the People of the State of Illinois,
|
represented in the General Assembly:
|
Section 5. The Environmental Protection Act is amended by |
adding Section 22.59 as follows: |
(415 ILCS 5/22.59 new) |
Sec. 22.59. Pilot project for Will County and Grundy County |
pyrolysis or gasification facility. |
(a) As used in this Section: |
"Plastics" means polystyrene or any other synthetic |
organic polymer that can be molded into shape under heat and |
pressure and then set into a rigid or slightly elastic form. |
"Plastics gasification facility" means a manufacturing |
facility that: |
(1) receives only uncontaminated plastics that have |
been processed prior to receipt at the facility into a |
feedstock meeting the facility's specifications for a |
gasification feedstock; and |
(2) uses heat in an oxygen-deficient atmosphere to |
process the feedstock into fuels, chemicals, or chemical |
feedstocks that are returned to the economic mainstream in |
the form of raw materials or products. |
"Plastics pyrolysis facility" means a manufacturing |
|
facility that: |
(1) receives only uncontaminated plastics that have |
been processed prior to receipt at the facility into a |
feedstock meeting the facility's specifications for a |
pyrolysis feedstock; and |
(2) uses heat in the absence of oxygen to process the |
uncontaminated plastics into fuels, chemicals, or chemical |
feedstocks that are returned to the economic mainstream in |
the form of raw materials or products. |
(b) Provided that permitting and construction has |
commenced prior to July 1, 2025, a pilot project allowing for a |
pyrolysis or gasification facility in accordance with this |
Section is permitted for a locally zoned and approved site in |
either Will County or Grundy County. |
(c) To the extent allowed by federal law, uncontaminated |
plastics that have been processed into a feedstock meeting |
feedstock specifications for a plastics gasification facility |
or plastics pyrolysis facility, and that are further processed |
by such a facility and returned to the economic mainstream in |
the form of raw materials or products, are considered recycled |
and are not subject to regulation as waste. |
(d) The Agency may propose to the Board for adoption, and |
the Board may adopt, rules establishing standards for materials |
accepted as feedstocks by plastics gasification facilities and |
plastics pyrolysis facilities, rules establishing standards |
for the management of feedstocks at plastics gasification |
|
facilities and plastics pyrolysis facilities, and any other |
rules, as may be necessary to implement and administer this |
Section. |
(e) If permitting and construction for the pilot project |
under subsection (b) has not commenced by July 1, 2025, this |
Section is repealed.
|
Section 99. Effective date. This Act takes effect July 1, |
2020.
|