SB0074 - 104th General Assembly
| |||||||
| |||||||
| 1 | AMENDMENT TO SENATE BILL 74 | ||||||
| 2 | AMENDMENT NO. ______. Amend Senate Bill 74 by replacing | ||||||
| 3 | everything after the enacting clause with the following: | ||||||
| 4 | "Section 1. Short title. This Act may be cited as the State | ||||||
| 5 | Agency Retainage Act. | ||||||
| 6 | Section 5. Definitions. As used in this Act: | ||||||
| 7 | "Retainage" means a portion of moneys withheld from the | ||||||
| 8 | payment of a contract for a specified period of time to ensure | ||||||
| 9 | that a contractor or subcontractor completes a construction | ||||||
| 10 | project in the manner specified in the contract. "Retainage" | ||||||
| 11 | does not include (i) moneys withheld due to violations of | ||||||
| 12 | local, State, or federal laws or (ii) moneys withheld from | ||||||
| 13 | grants to entities for capital improvements to non-State | ||||||
| 14 | property. | ||||||
| 15 | "Satisfactory progress" means the advancement of project | ||||||
| 16 | work without deficiency and in accordance with industry | ||||||
| |||||||
| |||||||
| 1 | standards and the contractual schedule and budget. | ||||||
| 2 | "State agency" has the meaning given in Section 1-7 of the | ||||||
| 3 | Illinois State Auditing Act. | ||||||
| 4 | Section 10. Determination of satisfactory progress. | ||||||
| 5 | Subject to the limitations in Section 15, a State agency may | ||||||
| 6 | withhold as retainage a portion of the moneys from the payment | ||||||
| 7 | of a contract that is entered into on or after the effective | ||||||
| 8 | date of this Act if and only if the State agency determines | ||||||
| 9 | that satisfactory progress has not been achieved by a | ||||||
| 10 | contractor or subcontractor during any period for which a | ||||||
| 11 | payment is to be made. If the contractor or subcontractor has | ||||||
| 12 | displayed unsatisfactory performance on previous State agency | ||||||
| 13 | projects resulting in a low performance score or suspension of | ||||||
| 14 | prequalification, the State agency may apply retainage from | ||||||
| 15 | the beginning of the project. Retainage may not be used as a | ||||||
| 16 | substitute for good contract management, and the State agency | ||||||
| 17 | may not withhold funds without cause. Determinations to retain | ||||||
| 18 | and the specific amount to be withheld must be made by the | ||||||
| 19 | State agency on a case-by-case basis and must be based on an | ||||||
| 20 | assessment of past performance and the likelihood that such | ||||||
| 21 | performance will continue. The State agency shall re-evaluate | ||||||
| 22 | its determination at subsequent project milestones. | ||||||
| 23 | Section 15. Limitations on the amount of retainage. The | ||||||
| 24 | amount of retainage withheld may not exceed 10% of the amount | ||||||
| |||||||
| |||||||
| 1 | of the draw amounts submitted and approved under the terms of | ||||||
| 2 | the contract until the contract is 50% completed, may not | ||||||
| 3 | exceed 5% of the amount of the draw amounts submitted and | ||||||
| 4 | approved under the terms of the contract for the duration of | ||||||
| 5 | the contract, and may be decreased as the contract approaches | ||||||
| 6 | completion to recognize better than expected performance, the | ||||||
| 7 | ability to rely on alternative safeguards, and other factors. | ||||||
| 8 | Upon completion of all contract requirements, amounts retained | ||||||
| 9 | under this Act must be paid promptly. | ||||||
| 10 | Section 20. Limitations on retainage from subcontractors. | ||||||
| 11 | (a) Notwithstanding any other provision of law, if a State | ||||||
| 12 | agency has not withheld retainage from a payment to a | ||||||
| 13 | contractor on a project, then that contractor may not withhold | ||||||
| 14 | retainage from a payment to a subcontractor for the same | ||||||
| 15 | project. | ||||||
| 16 | (b) If a State agency has withheld retainage from a | ||||||
| 17 | contractor in accordance with Section 10, then the contractor | ||||||
| 18 | may withhold retainage from a payment to a subcontractor, but | ||||||
| 19 | only to the extent that the amount retained from payment to the | ||||||
| 20 | contractor by the State agency is attributable to a failure on | ||||||
| 21 | the part of the subcontractor to make satisfactory progress | ||||||
| 22 | with respect to the subcontractor's contractual obligations. | ||||||
| 23 | (c) This Section applies only to subcontracts entered into | ||||||
| 24 | on or after the effective date of this Act in connection with a | ||||||
| 25 | State construction contract that is subject to the provisions | ||||||
| |||||||
| |||||||
| 1 | of Section 10.". | ||||||
| 2 | Section 99. Effective date. This Act takes effect July 1, | ||||||
| 3 | 2026.". | ||||||