(65 ILCS 5/8-12-16) (from Ch. 24, par. 8-12-16)
    Sec. 8-12-16. The financially distressed city shall develop, adopt and submit to the Authority, within 30 days after this Division first becomes applicable to the city as provided in Section 8-12-4, a revised Budget for the remaining portion of what is the city's current fiscal year at the time this Division first becomes applicable to the city as provided in Section 8-12-4 and, thereafter, an annual Budget for each subsequent fiscal year. After adoption by the city, the city shall submit each Budget to the Authority for its approval not later than 60 days prior to the commencement of the fiscal year to which the Budget relates. The Authority shall approve or reject the Budget not later than 30 days prior to the commencement of the fiscal year. No Budget shall have force or effect without approval of the Authority. Each Budget shall be developed, submitted, approved and monitored in accordance with the following procedures:
    (1) Each Budget submitted by the financially distressed city shall be based upon revenue estimates approved or prepared by the Authority, as provided in paragraph (1) of Section 8-12-15.
    (2) Each Budget shall contain such information and detail as may be prescribed by the Authority. Any deficit for a fiscal year or any portion of a fiscal year to which any Budget relates shall be included as a current expense item for the succeeding fiscal year.
    (3) The Authority shall approve each Budget if, in its judgment, the Budget is complete with respect to providing a detailed accounting of revenues and expenditures, is reasonably capable of being achieved, will meet the requirement set forth in Section 8-12-14, and will be consistent with the Financial Plan in effect. Otherwise, the Authority shall reject the Budget. The Authority's review of the Budget shall be in accordance with generally accepted accounting principles and standards. No Budget submitted by the financially distressed city shall be arbitrarily or capriciously rejected by the Authority. Any rejection by the Authority of any Budget submitted by the city shall be in writing and shall state the reasons for the rejection. In the event of rejection, the Authority may prescribe a procedure and standards for revision of the Budget by the city.
    (4) The financially distressed city shall report to the Authority at such times and such manner as the Authority may direct, concerning the city's compliance with each Budget. The Authority may review the city's operations, obtain budgetary data and financial statements, require the city to produce reports, and have access to any other information in the possession of the city that the Authority deems relevant. The Authority may issue recommendations or directives within its powers to the city to assure compliance with the Budget. The city shall produce such budgetary data, financial statements, reports and other information and comply with such directives.
    (5) After approval of each Budget, the financially distressed city shall promptly notify the Authority of any material change in the revenue or expenditure estimates in the Budget. The city may submit to the Authority, or the Authority may require the city to submit, a supplemental Budget based upon revised revenue or expenditure estimates or for any other good reason. The Authority shall approve or reject each supplemental Budget pursuant to paragraph (3) of this Section.