Within 15 business days of receipt of the written prior notice of entry
the public utility, railroad or pipeline owner or operator shall investigate
and determine whether or not the proposed entry and installation or repair,
maintenance, or removal would create a dangerous condition threatening the
safety of the public or the safety of its employees or threatening to cause
an interruption of the furnishing of vital transportation, utility or pipeline
services and upon so finding shall so notify the community antenna television
company of such decision in writing. Initial determination of the existence
of such a dangerous condition or interruption of services shall be made
by the public utility, railroad or pipeline owner or operator whose real
estate or right of way is involved. In the event that the community antenna
television company disagrees with such determination, a determination of
whether such entry and installation, maintenance, repair or removal would
create such a dangerous condition or interrupt services shall be made by
a court of competent jurisdiction upon the application of such community
antenna television company. An initial written determination of a public
utility, railroad, or pipeline owner or operator timely made and transmitted
to the community antenna television company, in the absence of a determination
by a court of competent jurisdiction finding to the contrary, bars the entry of
the community antenna television company upon the real estate or right of
way for any purpose.
Any public utility, railroad or pipeline owner or operator may assert
a written claim against any community antenna television company for just
compensation within 30 days after written notice has been given in accordance
with this subparagraph (f). If, within 60 days after the receipt of such
claim for compensation, the community antenna television company has not
agreed to the amount claimed or some other amount acceptable to the public
utility, railroad or pipeline owner or operator, the public utility, railroad
or pipeline owner or operator may bring suit to enforce such claim for just
compensation in any court of competent jurisdiction and, upon timely demand,
may require that the amount of just compensation be determined by a jury.
Any such action shall be commenced within 6 months of the notice provided
for in this subparagraph (f). In any action brought to determine such just
compensation, the public utility, railroad or pipeline owner or operator
may submit such evidence as may be relevant to the issue of just compensation.
Neither the assertion of a claim for compensation nor the initiation of
legal action to enforce such claim shall delay or impair the right of the
community antenna television company to construct or install cable television
facilities upon any real estate or rights of way of any public utility,
railroad or pipeline owner or operator.
To the extent that the public utility, railroad, or owner or operator
of an oil, petroleum product, chemical or gas pipeline deems it appropriate
to supervise, monitor or otherwise assist the community antenna television
company in connection with the installation, maintenance, repair or removal
of cable television facilities upon such real estate or rights of way, the
community antenna television company shall reimburse the public utility,
railroad or owner or operator of an oil, petroleum product, chemical or gas
pipeline for costs reasonable and actually incurred in connection therewith.
The provisions of this subparagraph (f) shall not be applicable to any
easements, rights of way or ways for public service facilities in which
public utilities, other than railroads, have any interest pursuant to "an
Act to revise the law in relation to plats" approved March 21, 1874, and
all ordinances enacted pursuant thereto. Such easements, rights of way
and ways for public service facilities are hereby declared to be apportionable
and upon written request by a community antenna television company, public
utilities shall make such easements, rights of way and ways for public service
facilities available for the construction, maintenance, repair or removal of
cable television facilities provided that such construction, maintenance,
repair or removal does not create a dangerous condition threatening the safety
of the public or the safety of such public utility employees or threatening
to cause an interruption of the furnishing of vital utility service. Initial
determination of the existence of such a dangerous condition or interruption
of services shall be made by the public utility whose easement, right of
way or way for public service facility is involved. In the event the community
antenna television company disagrees with such determination, a determination
of whether such construction, maintenance, repair or removal would create
such a dangerous condition or threaten to interrupt vital utility services,
shall be made by a court of competent jurisdiction upon the application
of such community antenna television company.
If a county notifies or a county requires a developer to notify a public
utility
before or after issuing a permit or other authorization for the construction of
residential
buildings, then the county or developer shall, at the same time, similarly
notify any
community antenna television system franchised by or within that county.
In addition to such other notices as may be required by this subparagraph
(f), a community antenna television company shall not enter upon the real
estate or rights of way of any public utility, railroad or pipeline owner
or operator for the purposes of above-ground maintenance or repair of its
television cable facilities without giving 96 hours prior written notice
to the registered agent of the public utility, railroad or pipeline owner
or operator involved, or in the case of a public utility, notice may be
given through the statewide one-call notice system provided for by General
Order of the Illinois Commerce Commission or, if in Chicago, through the
system known as the Chicago Utility Alert Network.
(Source: P.A. 93-219, eff. 1-1-04.)
|