(50 ILCS 20/20.10)
    (Section scheduled to be repealed on June 1, 2013)
    Sec. 20.10. Small design-build projects. In any case where the total overall cost of the project is estimated to be less than $12,000,000, the Commission may combine the two-phase procedure for design-build selection described in Section 20.5 into one combined step, provided that all the requirements of evaluation are performed in accordance with Section 20.5.
    This Section is repealed 5 years after the effective date of this amendatory Act of the 95th General Assembly.
(Source: P.A. 95-595, eff. 6-1-08.)