(30 ILCS 500/35-40) Sec. 35-40. Subcontractors. (a) Any contract granted under this Article shall state whether the services
of a subcontractor will be used. The contract shall include the names and
addresses of all subcontractors and the expected amount of money each will
receive under the contract. (b) If at any time during the term of a contract, a contractor adds or
changes any subcontractors, he or she shall promptly notify, in writing, the chief procurement officer for matters other than construction
or the higher education chief
procurement officer, whichever is appropriate, and the
responsible State purchasing officer, or their
designee of the names and addresses and the
expected amount of money each new or replaced subcontractor will receive.(Source: P.A. 95-481, eff. 8-28-07; 96-920, eff. 7-1-10.)|