Full Text of HB3523 99th General Assembly
HB3523ham001 99TH GENERAL ASSEMBLY | Rep. Adam Brown Filed: 3/12/2015
| | 09900HB3523ham001 | | LRB099 09392 MLM 32299 a |
|
| 1 | | AMENDMENT TO HOUSE BILL 3523
| 2 | | AMENDMENT NO. ______. Amend House Bill 3523 by replacing | 3 | | everything after the enacting clause with the following:
| 4 | | "Section 1. Short title. This Act may be cited as the Wind | 5 | | Energy Facilities Agricultural Impact Mitigation Act. | 6 | | Section 5. Purpose. The primary purpose of this Act is to | 7 | | promote the State's welfare by protecting landowners during the | 8 | | construction and deconstruction of commercial wind energy | 9 | | facilities. | 10 | | Section 10. Definitions.
As used in this Act:
| 11 | | "Agricultural impact mitigation agreement" means an | 12 | | agreement between the commercial wind energy facility owner and | 13 | | the Department of Agriculture described in Section 15 of this | 14 | | Act.
| 15 | | "Commercial wind energy facility" means a wind energy |
| | | 09900HB3523ham001 | - 2 - | LRB099 09392 MLM 32299 a |
|
| 1 | | conversion facility of equal or greater than 500 kilowatts in | 2 | | total nameplate generating capacity that has not already been | 3 | | constructed or received a permit by a decision of a county or | 4 | | municipality prior to the effective date of this Act. However, | 5 | | a wind energy conversion facility seeking an extension of a | 6 | | permit granted by a county or municipality prior to the | 7 | | effective date of this Act shall be considered a commercial | 8 | | wind energy facility.
| 9 | | "Commercial wind energy facility owner" means a private | 10 | | commercial enterprise that owns or operates a commercial wind | 11 | | energy facility.
| 12 | | "Construction" means the installation, preparation for | 13 | | installation, or repair of a commercial wind energy facility.
| 14 | | "Deconstruction" means the removal of a commercial wind | 15 | | energy facility from the property of a landowner and the | 16 | | restoration of that property as provided in the agricultural | 17 | | impact mitigation agreement.
| 18 | | "Department" means the Department of Agriculture.
| 19 | | "Landowner" means any person (1) with an ownership interest | 20 | | in property that is used for agricultural purposes and (2) that | 21 | | is a party to an underlying agreement.
| 22 | | "Underlying agreement" means the written agreement with a | 23 | | landowner, including, but not limited to, an easement, option, | 24 | | lease, or license, under the terms of which another person has | 25 | | constructed, constructs, or intends to construct a commercial | 26 | | wind energy facility on the property of the landowner. |
| | | 09900HB3523ham001 | - 3 - | LRB099 09392 MLM 32299 a |
|
| 1 | | Section 15. Agricultural impact mitigation agreement.
| 2 | | (a) A commercial wind energy facility owner of a commercial | 3 | | wind energy facility located on landowner property shall enter | 4 | | into an agricultural impact mitigation agreement with the | 5 | | Department outlining construction and deconstruction standards | 6 | | and policies designed to preserve the integrity of any | 7 | | agricultural land that is impacted by commercial wind energy | 8 | | facility construction and deconstruction.
| 9 | | (b) The agricultural impact mitigation agreement shall | 10 | | include, but is not limited to, such items as restoration of | 11 | | agricultural land affected by construction, deconstruction, | 12 | | construction staging, and storage areas; support structures; | 13 | | aboveground facilities; guy wires and anchors; underground | 14 | | cabling depth; topsoil replacement; protection and repair of | 15 | | agricultural drainage tiles; rock removal; repair of | 16 | | compaction and rutting; land leveling; prevention of soil | 17 | | erosion; repair of damaged soil conservation practices; | 18 | | compensation for damages to private property; clearing of trees | 19 | | and brush; interference with irrigation systems; access roads; | 20 | | weed control; pumping of water from open excavations; advance | 21 | | notice of access to private property; indemnification of | 22 | | landowners; and deconstruction plans and financial assurance | 23 | | for deconstruction.
| 24 | | (c) For commercial wind energy facility owners seeking a | 25 | | permit from a county or municipality for the construction of a |
| | | 09900HB3523ham001 | - 4 - | LRB099 09392 MLM 32299 a |
|
| 1 | | commercial wind energy facility, the agricultural impact | 2 | | mitigation agreement shall be entered into prior to the public | 3 | | hearing required prior to a siting decision of a county or | 4 | | municipality regarding the commercial wind energy facility. | 5 | | The agricultural impact mitigation agreement is binding on any | 6 | | subsequent commercial wind energy facility owner that takes | 7 | | ownership of the commercial wind energy facility that is the | 8 | | subject of the agreement.
| 9 | | (d) If a commercial wind energy facility owner seeks an | 10 | | extension of a permit granted by a county or municipality for | 11 | | the construction of a commercial wind energy facility prior to | 12 | | the effective date of this Act, the agricultural impact | 13 | | mitigation agreement shall be entered into prior to a decision | 14 | | by the county or municipality to grant the permit extension.
| 15 | | (e) The Department shall adopt rules that are necessary and | 16 | | appropriate for the implementation and administration of | 17 | | agricultural impact mitigation agreements as required under | 18 | | this Act.
| 19 | | Section 90. The Counties Code is amended by changing | 20 | | Section 5-12020 as follows: | 21 | | (55 ILCS 5/5-12020) | 22 | | Sec. 5-12020. Wind farms. A county may establish standards | 23 | | for wind farms and electric-generating wind devices. The | 24 | | standards may include, without limitation, the height of the |
| | | 09900HB3523ham001 | - 5 - | LRB099 09392 MLM 32299 a |
|
| 1 | | devices and the number of devices that may be located within a | 2 | | geographic area. A county may also regulate the siting of wind | 3 | | farms and electric-generating wind devices in unincorporated | 4 | | areas of the county outside of the zoning jurisdiction of a | 5 | | municipality and the 1.5 mile radius surrounding the zoning | 6 | | jurisdiction of a municipality. There shall be at least one | 7 | | public hearing not more than 30 days prior to a siting decision | 8 | | by the county board. Notice of the hearing shall be published | 9 | | in a newspaper of general circulation in the county. A | 10 | | commercial wind energy facility owner, as defined in the Wind | 11 | | Energy Facilities Agricultural Impact Mitigation Act, must | 12 | | enter into an agricultural impact mitigation agreement with the | 13 | | Department of Agriculture prior to the date of the required | 14 | | public hearing. A commercial wind energy facility owner seeking | 15 | | an extension of a permit granted by a county prior to the | 16 | | effective date of this amendatory Act of the 99th General | 17 | | Assembly must enter into an agricultural impact mitigation | 18 | | agreement with the Department of Agriculture prior to a | 19 | | decision by the county to grant the permit extension. Counties | 20 | | may allow test wind towers to be sited without formal approval | 21 | | by the county board. Any provision of a county zoning ordinance | 22 | | pertaining to wind farms that is in effect before the effective | 23 | | date of this amendatory Act of the 95th General Assembly may | 24 | | continue in effect notwithstanding any requirements of this | 25 | | Section. | 26 | | A county may not require a wind tower or other renewable |
| | | 09900HB3523ham001 | - 6 - | LRB099 09392 MLM 32299 a |
|
| 1 | | energy system that is used exclusively by an end user to be | 2 | | setback more than 1.1 times the height of the renewable energy | 3 | | system from the end user's property line.
| 4 | | (Source: P.A. 95-203, eff. 8-16-07; 96-306, eff. 1-1-10; | 5 | | 96-566, eff. 8-18-09; 96-1000, eff. 7-2-10.) | 6 | | Section 95. The Illinois Municipal Code is amended by | 7 | | changing Section 11-13-26 as follows: | 8 | | (65 ILCS 5/11-13-26) | 9 | | Sec. 11-13-26. Wind farms. | 10 | | (a) A municipality may regulate wind farms and | 11 | | electric-generating wind devices within its zoning | 12 | | jurisdiction and within the 1.5 mile radius surrounding its | 13 | | zoning jurisdiction. There shall be at least one public hearing | 14 | | not more than 30 days prior to a siting decision by the | 15 | | corporate authorities of a municipality. Notice of the hearing | 16 | | shall be published in a newspaper of general circulation in the | 17 | | municipality. A commercial wind energy facility owner, as | 18 | | defined in the Wind Energy Facilities Agricultural Impact | 19 | | Mitigation Act, must enter into an agricultural impact | 20 | | mitigation agreement with the Department of Agriculture prior | 21 | | to the date of the required public hearing. A commercial wind | 22 | | energy facility owner seeking an extension of a permit granted | 23 | | by a municipality prior to the effective date of this | 24 | | amendatory Act of the 99th General Assembly must enter into an |
| | | 09900HB3523ham001 | - 7 - | LRB099 09392 MLM 32299 a |
|
| 1 | | agricultural impact mitigation agreement with the Department | 2 | | of Agriculture prior to a decision by the municipality to grant | 3 | | the permit extension. A municipality may allow test wind towers | 4 | | to be sited without formal approval by the corporate | 5 | | authorities of the municipality. Test wind towers must be | 6 | | dismantled within 3 years of installation. For the purposes of | 7 | | this Section, "test wind towers" are wind towers that are | 8 | | designed solely to collect wind generation data.
| 9 | | (b) A municipality may not require a wind tower or other | 10 | | renewable energy system that is used exclusively by an end user | 11 | | to be setback more than 1.1 times the height of the renewable | 12 | | energy system from the end user's property line. A setback | 13 | | requirement imposed by a municipality on a renewable energy | 14 | | system may not be more restrictive than as provided under this | 15 | | subsection. This subsection is a limitation of home rule powers | 16 | | and functions under subsection (i) of Section 6 of Article VII | 17 | | of the Illinois Constitution on the concurrent exercise by home | 18 | | rule units of powers and functions exercised by the State. | 19 | | (Source: P.A. 95-203, eff. 8-16-07; 96-306, eff. 1-1-10.)
| 20 | | Section 99. Effective date. This Act takes effect upon | 21 | | becoming law.".
|
|