SJ0073sam002 98TH GENERAL ASSEMBLY

 


 
SJ0073SAM002LRB098 21037 GRL 59562 a

1
AMENDMENT TO SENATE JOINT RESOLUTION 73

2    AMENDMENT NO. ___. Amend Senate Joint Resolution 73, AS
3AMENDED, by replacing everything after the heading with the
4following:
 
5    "WHEREAS, Numerous development projects are occurring in
6Illinois, including roads, electric transmission lines, and
7pipelines; and
 
8    WHEREAS, Landowners are often unaware their land is being
9considered for a project until they are contacted by a field
10agent; and
 
11    WHEREAS, An open line of communication often eases
12landowner concerns and helps preserve the integrity of any land
13impacted by construction; therefore, be it
 
14    RESOLVED, BY THE SENATE OF THE NINETY-EIGHTH GENERAL

 

 

SJ0073SAM002- 2 -LRB098 21037 GRL 59562 a

1ASSEMBLY OF THE STATE OF ILLINOIS, THE HOUSE OF REPRESENTATIVES
2CONCURRING HEREIN, that, in the taking of land or seeking of
3easements by eminent domain or quick-take procedures for
4development projects, the Senate recommends the following
5steps be followed by the entity developing the project:
6        (1) Notify affected landowners about the potential
7    project as soon as possible and provide a reliable time
8    frame for development activities;
9        (2) Notify a landowner prior to entering the
10    landowner's private property for any reason;
11        (3) Keep work crews within the working easement;
12        (4) If applicable, ensure all field drainage tiles are
13    repaired by a drain tile contractor chosen after
14    consultation with the landowner, including repairing
15    drainage issues discovered after the project is completed;
16        (5) Ensure that road closings are limited and
17    appropriate detour access is provided;
18        (6) Ensure that run off and storm water are
19    appropriately managed;
20        (7) Assign a point person before, during, and after the
21    process who will be responsible for assuring a credible
22    communication process and for taking appropriate action
23    when notified by landowners; and
24        (8) Inform landowners about any pertinent State
25    agriculture impact mitigation agreements and inform them
26    that the provisions of those agreements may be the minimum

 

 

SJ0073SAM002- 3 -LRB098 21037 GRL 59562 a

1    standards for impact mitigation that could be included in
2    landowner agreements or contracts.".