Section 467.APPENDIX B
Application
Large Interconnection
Request Application Form
(Greater than 10
MVA)
Applicant Contact Information
|
Name:
|
|
|
Company:
|
|
|
Mailing Address:
|
|
|
City:
|
|
State:
|
|
Zip Code:
|
|
|
Telephone (Primary):
|
|
(Alternate):
|
|
|
Facsimile Number:
|
|
E-Mail Address:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Alternative or Designated Representative Contact
Information
|
Name:
|
|
|
Company:
|
|
|
Mailing Address:
|
|
|
City:
|
|
State:
|
|
Zip Code:
|
|
|
Telephone (Primary):
|
|
(Alternate):
|
|
|
Facsimile Number:
|
|
E-Mail Address:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Distributed Generation Facility
Information
|
Project Name:
|
|
|
Facility Address:
|
|
|
City:
|
|
County:
|
|
State:
|
|
Zip Code:
|
|
|
Electric Distribution Company
(EDC) serving Facility site:
|
|
|
Electric Supplier (if
different from EDC):
|
|
|
Account Number of Facility
site (existing EDC customers):
|
|
|
Inverter Manufacturer:
|
|
Model:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Equipment Contractor (if known):
|
Name:
|
|
|
Mailing Address:
|
|
|
City:
|
|
State:
|
|
Zip Code:
|
|
|
Telephone (Primary):
|
|
(Alternate):
|
|
|
Facsimile Number:
|
|
E-Mail Address:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Electrical Contractor (if known):
|
Name:
|
|
|
Mailing Address:
|
|
|
City:
|
|
State:
|
|
Zip Code:
|
|
|
Telephone (Primary):
|
|
(Alternate):
|
|
|
Facsimile Number:
|
|
E-Mail Address:
|
|
|
License number:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Existing Electric Service Information for Customer
Facility Where Generator Will Be Interconnected
Check here if there is no existing electric service at the
site
|
Capacity:
|
|
(Amps)
|
Voltage:
|
|
(Volts)
|
|
Type of Service:
|
Single Phase
|
Three Phase
|
|
(If customer-provided) Three Phase Transformer, Indicate
Type:
|
|
Primary Winding
|
Wye
|
Delta
|
|
Secondary Winding
|
Wye
|
Delta
|
|
Transformer Size:
|
|
Impedance:
|
|
|
Point of Interconnection − Brief Description and
Address of the Distributed Generation
|
|
Location:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Intent of Generation (check all
that apply):
Offset Load (Unit will operate in parallel, but will not export power to EDC)
Back-up Generation (Units that temporarily operate in parallel with the electric
distribution system for more than 100 milliseconds)
Qualified Facility ("QF") under PURPA
Note: Backup
units that do not operate in parallel for more than 100 milliseconds do not
need an interconnection agreement.
Generator & Prime Mover Information
|
ENERGY SOURCE (Hydro, Wind,
Solar, Process Byproduct, Biomass, Oil, Natural Gas, Coal, etc.):
|
|
ENERGY CONVERTER TYPE (Wind
Turbine, Photovoltaic Cell, Fuel Cell, Steam Turbine, etc.):
|
|
GENERATOR
SIZE:
kW
or kVA
|
NUMBER OF UNITS:
|
TOTAL
CAPACITY:
kW
or kVA
|
|
GENERATOR
TYPE (Check one):
Induction Inverter Synchronous Other 3515March 1, 2010
|
Distributed Generation Facility Information
Estimated Commissioning Test Date:
_________________________________
Note: Provide
the following information to the extent known. The EDC will contact you for
additional information that may be needed after reviewing the application.
List interconnection components/systems to be used in the
distributed generation facility.
|
Component/System
|
NRTL Providing Label & Listing
|
|
1.
|
|
|
2.
|
|
|
3.
|
|
|
4.
|
|
|
5.
|
|
|
|
|
Please provide
copies of manufacturer brochures or technical specifications
Energy Production Equipment/Inverter Information:
|
Synchronous
|
Induction
|
Inverter
|
Other
|
|
|
Rating:
|
|
kW
|
Rating:
|
|
kVA
|
|
Rated Voltage:
|
|
Volts
|
|
Rated Current:
|
|
Amps
|
|
System Type Tested (Total System):
|
|
Yes
|
|
No; attach product literature
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For Synchronous Machines:
|
Manufacturer (when available):
|
|
|
Model No. (when available):
|
|
Version No. (when available):
|
|
|
Submit copies of the Saturation Curve and the Vee Curve
|
|
Salient
|
Non-Salient
|
|
Rated RPM:
|
|
Field Amperes:
|
|
at rated generator
|
|
voltage and current and
|
|
% PF over-excited
|
|
Type of Exciter:
|
|
|
Output Power of Exciter:
|
|
|
Type of Voltage Regulator:
|
|
Locked Rotor
|
|
Synchronous Speed:
|
|
RPM
|
|
Winding Connection:
|
|
Min.
Operating Freq:
|
|
|
Generator Connection:
|
Delta
|
Wye
|
Wye Grounded
|
|
Direct-axis Synchronous Reactance:
|
(Xd)
|
|
ohms
|
|
Direct-axis Transient Reactance:
|
(X'd)
|
|
ohms
|
|
Direct-axis Sub-transient Reactance:
|
(X''d)
|
|
ohms
|
|
Negative Sequence Reactance:
|
|
ohms
|
|
Zero Sequence Reactance:
|
|
ohms
|
|
Neutral Impedance or
Grounding Resister (if any):
|
|
ohms
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For Induction Machines:
|
Manufacturer:
|
|
|
|
Model No.:
|
|
Version No.:
|
|
|
|
Locked Rotor Current:
|
|
Amps
|
|
Rotor Resistance (Rr):
|
|
ohms
|
Exciting Current:
|
|
Amps
|
|
Rotor Reactance (Xr):
|
|
ohms
|
Reactive Power Required:
|
|
|
|
Magnetizing Reactance (Xm):
|
|
ohms
|
|
VARs (No Load)
|
|
Stator Resistance (Rs):
|
|
ohms
|
|
VARs (Full Load)
|
|
Stator Reactance (Xs):
|
|
ohms
|
|
Short Circuit Reactance (X"d):
|
|
ohms
|
|
Phases:
|
Single Three
Phase
|
|
|
Frame Size:
|
|
Design Letter:
|
|
Temp. Rise:
|
|
°C.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Reverse Power Relay Information
|
Manufacturer:
|
|
|
Relay Type:
|
|
Model Number:
|
|
|
Reverse Power Setting:
|
|
|
Reverse Power Time Delay (if any):
|
|
|
|
|
|
|
|
|
Additional Information for Inverter-Based Facilities
Inverter Information:
|
Manufacturer:
|
|
Model:
|
|
|
|
Type:
|
Forced Commutated
|
Line Commutated
|
|
Rated Output:
|
|
Watts
|
|
Volts
|
|
Efficiency:
|
|
%
|
Power Factor:
|
|
%
|
|
Inverter UL 1741 Listed:
|
Yes
|
No
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DC Source / Prime Mover:
|
Rating:
|
|
kW
|
Rating:
|
|
kVA
|
|
Rated Voltage:
|
|
Volts
|
|
Open Circuit Voltage (if applicable):
|
|
Volts
|
|
Rated Current:
|
|
Amps
|
|
Short Circuit Current (if applicable):
|
|
Amps
|
|
|
|
|
|
|
|
|
|
|
|
|
Dedicated Transformer (applicant owned):
|
Rating:
|
|
MVA
|
|
Voltage Ratio:
|
|
/
|
|
kV
|
|
Fixed Tap Setting:
|
|
|
|
Winding connections:
|
|
|
|
Impedance:
|
|
% based on transformer rating
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capacitor Banks:
Other Facility Information:
One Line Diagram attached: Yes
Plot Plan attached: Yes
|
Comments or additional information:
|
|
|
|
|
|
|
Customer Signature
I hereby certify that all of the information provided in
this Interconnection Request Application Form is true.
|
Applicant Signature:
|
|
|
Title:
|
|
Date:
|
|
|
|
|
|
|
An application fee must be submitted before the application
can be processed. The application fee is $15,000 for all Large (>10 MVA)
Distributed Generation Facilities. Of the total application fee, $5,000 is
nonrefundable, while the EDC shall apply the remaining $10,000 toward any
subsequent studies related to this application.
EDC Acknowledgement
Receipt of the application and fee is acknowledged. This
acknowledgement does not preclude the requirement to furnish additional
information by the applicant if requested by the EDC when it is necessary for
the EDC's review under these procedures. When this interconnection request is
deemed complete by the EDC, the EDC shall notify the interconnection customer
in writing.
|
EDC Signature:
|
|
Date:
|
|
|
Printed Name:
|
|
Title:
|
|
|
|
|
|
|
|