TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION
SUBCHAPTER c: ELECTRIC UTILITIES
PART 467 ELECTRIC INTERCONNECTION OF LARGE DISTRIBUTED GENERATION FACILITIES
SECTION 467.10 SCOPE


 

Section 467.10  Scope

 

The Illinois Large Distributed Generation Interconnection Standard applies to any generation facility operated in parallel with an electric public utility distribution company in Illinois and whose nameplate capacity is greater than 10 MVA (large distributed generation facility), provided that the distributed generation facility is not subject to the interconnection requirements of either the Federal Energy Regulatory Commission (FERC) or the applicable Regional Transmission Organization (RTO) (either Midwest Independent Transmission System Operator, Inc. (MISO) or PJM Interconnection, LLC (PJM)).