TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION SUBCHAPTER c: ELECTRIC UTILITIES PART 467 ELECTRIC INTERCONNECTION OF LARGE DISTRIBUTED GENERATION FACILITIES SECTION 467.10 SCOPE
Section 467.10 Scope
The Illinois Large Distributed Generation Interconnection Standard applies to any generation facility operated in parallel with an electric public utility distribution company in Illinois and whose nameplate capacity is greater than 10 MVA (large distributed generation facility), provided that the distributed generation facility is not subject to the interconnection requirements of either the Federal Energy Regulatory Commission (FERC) or the applicable Regional Transmission Organization (RTO) (either Midwest Independent Transmission System Operator, Inc. (MISO) or PJM Interconnection, LLC (PJM)). |