TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION
SUBCHAPTER c: ELECTRIC UTILITIES
PART 466 ELECTRIC INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES
SECTION 466.35 WAIVER


 

Section 466.35  Waiver

 

a)         The Commission may, on application or petition of an EDC, distributed generation applicant or customer, or on its own motion, grant a temporary or permanent waiver from this Part, or any Section or subsection of this Part, in individual cases in which the Commission finds that:

 

1)         the provision from which the waiver is granted is not statutorily mandated;

 

2)         no party will be injured by the granting of the waiver; and

 

3)         the rule from which the waiver is granted would, as applied to the particular case, be unreasonable or unnecessarily burdensome.

 

b)         The burden of proof in establishing a right to waiver shall be on the party seeking the waiver.

 

(Source:  Added at 41 Ill. Reg. 862, effective January 20, 2017)