TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION
SUBCHAPTER c: ELECTRIC UTILITIES
PART 465 NET METERING
SECTION 465.40 REPORTING REQUIREMENTS


 

Section 465.40  Reporting Requirements

 

The report required by Section 16-107.5(k) of the Act shall be filed with the Manager of the Energy Division of the Illinois Commerce Commission by April 1 of each year beginning in 2009.  The report shall include all information required under Section 16-107.5(k) of the Act, including, but not limited to, the following information:  the total peak demand supplied by the electricity provider during the previous year; the total generating capacity of its net metering customers; whether the electricity provider intends to limit total generating capacity of its net metering customers to 1%; and the electricity provider's total number of net metering customers.