TITLE 71: PUBLIC BUILDINGS, FACILITIES AND REAL PROPERTY
CHAPTER IV: SECRETARY OF STATE PART 2000 PUBLIC BUILDING CONSTRUCTION SECTION 2000.310 DELAY IN AWARD
Section 2000.310 Delay in Award
Should administrative difficulties, such as delay in approval from LSNC, fiscal problems, acts of God, death of parties, and utility failures, be encountered after bid opening which may delay award beyond Bidders' acceptance periods, the responsive Bidders may be requested, before expiration of their bids, to extend the bid acceptance period (with consent of sureties, if any) in order to avoid the need for readvertisement. |