TITLE 44: GOVERNMENT CONTRACTS, PROCUREMENT AND PROPERTY MANAGEMENT
SUBTITLE A: PROCUREMENT AND CONTRACT PROVISIONS
CHAPTER IV: CHIEF PROCUREMENT OFFICER FOR CAPITAL DEVELOPMENT BOARD
PART 8 PROCUREMENT PRACTICES
SECTION 8.170 ALTERNATIVE DISPUTE RESOLUTION


 

Section 8.170  Alternative Dispute Resolution

 

To resolve disputes related to the performance of construction projects, whether in design phase or construction phase, the parties to the dispute shall utilize alternative dispute resolution methods as required by the contract or bid documents.  At a minimum, alternative dispute resolutions shall be a condition precedent to the filing of any court action valued in excess of $50,000.  This Section shall not apply to mechanics lien actions, unless the parties thereto so consent, nor to contract terminations, CDB's right to carry out the work, and non-project matters such as suspension of prequalification.