SECTION 660.240 AWARD AFTER BID EVALUATION


 

Section 660.240  Award After Bid Evaluation

 

a)         Unless all bids are rejected, an award notification will be made to the lowest responsible bidder whose bid is responsive to and conforms with the requirements and criteria of the invitation.  Tie bids will be decided by lot. All responsibility, responsiveness, and price factors are considered so as to select the bid most advantageous to the State.  An individual contract item advertised in an Invitation for Bids may state other, additional award and evaluation criteria that will be capable of objective consideration for award.  (See Section 20-10(g) of the Code.)

 

b)         Responsibility of bidders for construction contracts is determined in accordance with the Department's rules for Prequalification of Contractors and Issuance of Plans and Proposals found at 44 Ill. Adm. Code 650.

 

c)         For nonconstruction contracts, the responsibility of bidders will be determined based upon the following factors unless some other or additional factors or prequalification procedures are stated in the Invitation for Bids.

 

1)         The bidder shall possess the appropriate financial, material, equipment, facility and personnel resources and expertise necessary to meet all contractual obligations.

 

2)         The bidder shall have a satisfactory record of performance, including but not limited to a sound record of integrity and business ethics.

 

3)         The bidder shall be under no legal disability of any kind to contract with the State.

 

4)         The bidder shall have submitted all information requested by the Invitation for Bids concerning responsibility.