![]() |
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE C: WATER POLLUTION CHAPTER II: ENVIRONMENTAL PROTECTION AGENCY PART 369 PROCEDURES FOR PROVIDING FINANCIAL ASSISTANCE FROM THE WATER POLLUTION CONTROL LOAN PROGRAM UNDER THE AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 SECTION 369.460 LIMITATION ON DESIGN COST
Section 369.460 Limitation on Design Cost
Allowable costs for design of the loan project will be limited to the actual cost incurred for design, up to a maximum percentage of the allowable as bid construction cost.
a) For allowable as bid construction costs of $500,000 or less, the design will be funded up to 15%;
b) For allowable as bid construction costs of $500,001 to $2,000,000, the design will be funded up to 12%;
c) For allowable as bid construction costs of $2,000,001 to $5,000,000, the design will be funded up to 10%;
d) For allowable as bid construction costs of $5,000,001 to $10,000,000, the design will be funded up to 8%; and
e) For allowable as bid construction costs of more than $10,000,000, the design will be funded up to 7%. |