Section 365.460 Limitation on Design Cost
Allowable costs for design of the loan project will be limited to the actual cost incurred for design up to a maximum percentage of the allowable as bid construction cost.
a) For allowable as bid construction costs of $500,000 or less, the design will be funded up to 15%;
b) For allowable as bid construction costs of $500,001 to $2,000,000, the design will be funded up to 12%;
c) For allowable as bid construction costs of $2,000,001 to $5,000,000, the design will be funded up to 10%;
d) For allowable as bid construction costs of $5,000,001 to $10,000,000, the design will be funded up to 8%; and
e) For allowable as bid construction costs of more than $10,000,000, the design will be funded up to 7%.
(Source: Amended at 30 Ill. Reg. 15590, effective September 18, 2006) |